POSTER 06
Section 2 · PMBOK 7 — The Practitioner's Toolkit

Models, Methods & Artifacts

PMBOK 7 stops prescribing process and instead gives a toolkit you tailor (Poster 5). Three families: Models are thinking frameworks that explain a situation; Methods are the means to produce an output; Artifacts are the templates, documents & deliverables you create.

MODELS — ways to think

  • Situational leadership: flex style (direct → coach → support → delegate) to follower readiness.
  • Communication: sender–receiver, channels = n(n−1)/2, cross-cultural & effectiveness models.
  • Motivation: Maslow (hierarchy) · Herzberg (hygiene vs motivators) · McGregor (Theory X / Y) · intrinsic vs extrinsic · Pink (Autonomy·Mastery·Purpose).
  • Change: ADKAR · Kotter 8-Step · Bridges Transition (ending→neutral→beginning) · Satir curve.
  • Complexity: Cynefin (clear / complicated / complex / chaotic) · Stacey matrix.
  • Team development: Tuckman (Forming·Storming·Norming·Performing·Adjourning) · Drexler–Sibbet.
  • Conflict: Thomas–Kilmann — Compete · Collaborate · Compromise · Avoid · Accommodate.
  • Stakeholders: Salience (Power·Legitimacy·Urgency) · Power/Interest grid.
  • Process / planning: PDCA · OODA · escalation & negotiation models.

METHODS — ways to do

  • Data gathering: brainstorming · interviews · focus groups · benchmarking · surveys · checklists.
  • Data analysis: alternatives · cost-benefit · earned value · forecasting · root-cause · variance · trend · what-if · SWOT · regression · reserve · assumption/constraint.
  • Estimating: analogous (top-down) · parametric · three-point / PERT · bottom-up · affinity (story points, t-shirt sizing).
  • Decision-making: voting / fist-of-five · multicriteria (MCDA) · weighted scoring.
  • Data representation: see Artifacts → "visual data & information".
  • Meetings & events: stand-ups · reviews · retrospectives · planning · kick-offs.

ARTIFACTS — things you show

  • Strategy: business case · project brief · charter · roadmap.
  • Logs & registers: assumption · backlog · change · issue · lessons-learned · risk · stakeholder (RAID).
  • Plans: PM plan + subsidiary plans (scope, schedule, cost, quality, comms, risk, etc.).
  • Baselines: scope · schedule · cost · the integrated performance measurement baseline (PMB).
  • Hierarchy charts: WBS · OBS · RBS (risk & resource breakdown).
  • Visual data & info: Gantt · burn-up/down · cumulative flow (CFD) · S-curve · RACI · dashboard · story map · value stream map.
  • Reports: status · progress · quality · risk reports.
  • Agreements / contracts: FFP · T&M · CPFF · CPIF.

High-Yield Exam Concepts

  • Contract risk: FFP = most risk on seller; CPFF / cost-plus = most risk on buyer; T&M = shared.
  • PERT (expected) = (O + 4M + P) / 6  ·  PERT σ = (P − O) / 6.
  • Communication channels = n(n − 1) / 2.
  • Baseline = approved version + approved changes; measure actuals against it.
  • Know cold: Tuckman stages · Cynefin domains · Thomas-Kilmann modes · Salience · ADKAR vs Kotter.
  • Match the tool to the context — there is no single "right" set.

Executive View

  • Standardise a core toolkit; let teams tailor the rest.
  • Dashboards & S-curves are the artifacts that reach the board.
  • Contract type = a strategic risk-allocation lever, not an admin detail.

Industry Example — Manufacturing Transformation (Lean Cell)

Manufacturing
  • Models: Cynefin to classify the change · Kotter + ADKAR to drive shop-floor adoption · Tuckman to read the new cell team.
  • Methods: cost-benefit + parametric estimate to justify the cell · root-cause (5 Whys) on defects · what-if for capacity.
  • Artifacts: business case · WBS · risk register · S-curve · RACI · value stream map of the line.

Memory Hooks

  • "Models think · Methods do · Artifacts show."
  • Tuckman: "Form a Storm, Normally Perform, then Adjourn."
  • Artifacts = the PM's paper trail (logs record, baselines compare, reports communicate).
60-sec Review Define model / method / artifact Recite PERT + channels formulas Who holds risk: FFP vs CPFF List Tuckman's 5 stages Name 3 visual-data artifacts
PMI Visual Wall · Poster 06 · PMBOK 7 Models, Methods & Artifacts · original instructional design · A3 landscape